In week 9, my team continued to rapid prototype various components of the track. We also tested the bending machine in the workshop, and realized that the accuracy of the machine is not suitable for the tolerances of our project. With this complication, my team has to reconsider alternative methods to bend the aluminum. We also had to reconsider the size of aluminum that we would be using for the project.
Friday, November 3, 2017
Fall 2017, Weeks 8 and 9: Presentation 2 and Support Structure
In week 8 of the Spartan Superway project, our team presented our second presentation for the semester. After presenting our material, our peers pointed out that our designed support structure required an additional leveling system for un-leveled ground. My team considered ideas such as drilling holes through the support base to insert 4 adjustable bolts. This would allow us to angle the support as needed.
Subscribe to:
Post Comments (Atom)
Spring 2018, Week 15: Completing the Final Presentation
May 9, 2018 On Wednesday, we came into the SSDC to adjust any sections that would cause the bogie to bind. We re-bent a curve section, as ...
-
April 11, 2018 This week, our team presented our second presentation of the semester. In this presentation, I reiterated the design r...
-
May 9, 2018 On Wednesday, we came into the SSDC to adjust any sections that would cause the bogie to bind. We re-bent a curve section, as ...
-
March 21, 2018 This week, our team attempted to create curve sections with the bender Kevin manufactured. As shown Figure 1, it seems that...