This week, we toured the facility for the Spartan Superway Project. We were shown the existing track and bogie system for the full scale model, as well as the 12th scale model system.
In addition, we were assigned into sub-project teams. I have been assigned to work on the track system for the 12th scale model. In our sub-teams, we created a blog to keep track of our work for the project. The link for this blog is spartantrackteam.blogspot.com. Using a new adopted track system, our goal for this project is to create a track that will encompass the existing model. We hope to have a functional track by next spring.
Subscribe to:
Post Comments (Atom)
Spring 2018, Week 15: Completing the Final Presentation
May 9, 2018 On Wednesday, we came into the SSDC to adjust any sections that would cause the bogie to bind. We re-bent a curve section, as ...
-
May 9, 2018 On Wednesday, we came into the SSDC to adjust any sections that would cause the bogie to bind. We re-bent a curve section, as ...
-
May 2, 2018 Throughout the week, our team managed to complete all the sections of the track. Early in the week, I managed to assemble the ...
-
March 21, 2018 This week, our team attempted to create curve sections with the bender Kevin manufactured. As shown Figure 1, it seems that...
No comments:
Post a Comment